 |
|
to fill out a simple form to connect to Personal Injury Lawyers in your area.
|
|
|
|
|
AMERICAN TOWERS OWNERS v. CCI MECHANICAL12/20/1996
Plaintiff American Towers Owners Association, Inc. (the Association), brought this action against numerous defendants, alleging design and construction defects in the plumbing and mechanical systems of a large condominium complex. The district court granted defendants' motions for summary judgment, and the Association appeals.
BACKGROUND
In reviewing this grant of summary judgment, we view the facts in the light most favorable to the Association and recite them accordingly. The American Towers complex consists of two 26-story towers containing 357 residential units and some commercial space. Architectural services for the complex commenced in 1980, and a general contractor was hired in 1981. The complex was substantially completed in July 1983.
Defendants were all involved in the complex's design, development, and construction. CCI Mechanical, Inc. (CCI), was the complex's mechanical subcontractor and engineer and was responsible for the planning and installation of the culinary water, sewer, heating, cooling, and fire protection systems. Christiansen Brothers, Inc., was the general contractor. American Towers, Inc., was the original developer and was one of the original borrowers on the complex's construction loan. Trossen Wright Architects, P.A., Donald A. Wright, and Duane A. Trossen were the architects. Block 58 Associates, Block Associates, Inc., Dee W. Christiansen, West Temple Associates, CL Management, Ltd., Howard S. Clark, the late George A. Leaming, and MB Management, Inc., were all involved in the development and/or financing of the complex. Daw Incorporated was the dry wall subcontractor. Hunter Insulation, Inc., was the insulation subcontractor. First Security Bank of Utah, N.A., and its wholly owned subsidiary REH Inc., foreclosed its security interest in 1984 and became a successor developer of the complex.
The Association's second amended complaint sought damages for unjust enrichment, breach of contract/warranty (third-party beneficiary), negligence, and breach of implied warranty. The allegations generally concern problems with the complex's plumbing and mechanical systems. For example, instead of using premanufactured T-shaped joints at the ninety degree plumbing connections, builders fabricated the joints on site. These joints were allegedly incorrectly made, resulting in thin walls that are inherently weaker than standard premanufactured joints. These weak joints began to progressively spring leaks in late 1990 as the complex reached full occupancy. Other problems include (1) piping systems that were installed without adequate provision for expansion and contraction and without sufficient guides and anchors, resulting in pipe breaks and leaks, (2) pipes that are too small in some locations, resulting in pressure loss and failures, (3) domestic water system pressure that exceeds the code limit at some fixtures, and (4) lack of outside air vents and exhaust systems.
First Security filed a motion to dismiss the complaint which the district court treated as
a motion for summary judgment. The court granted the motion, concluding that First Security entered into a May 1989 release with the Association that covered the claims asserted in the complaint and that the release was not subject to rescission on the basis of mutual mistake.
Most of the remaining defendants moved for summary judgment beginning in May 1994. In response, the Association moved for a continuance under rule 56(f) of the Utah Rules of Civil Procedure, on which motion the court apparently did not rule. In July 1994, the Association filed a second rule 56(f) motion.
The district court conducted a hearing in August 1994, denied
Page 1 2 3 4 5 6 7 8 9 10 11 12 13 Utah Personal Injury Attorneys
Personal Injury Lawyers
|
|
to fill out a simple form to connect to Personal Injury Lawyers in your area.
|
|
By using the system, you agree to TERMS OF SERVICE
|