Bush v. Roche Constructors Inc.8/15/1991
William G. and Colleen Bush, appeal from the summary judgment dismissing their complaint against defendants, Roche Constructors, Inc., and Francis Constructors, Inc., because their claims were not brought within six years of the date that defendants had completed their construction of a residential improvement. We affirm.
The complaint, which was filed July 10, 1989, claimed damages for losses resulting from the alleged improper construction of a deck and patio area at plaintiffs' residence. It is undisputed that construction of the deck and patio was completed in the fall of 1980 and that plaintiffs first became aware of structural damage to their deck, patio, and residence in 1988.
Defendants filed motions to dismiss the complaint, asserting that plaintiffs' claims were barred by § 13-80-104, C.R.S. (1987 Repl. Vol. 6A), the six-year statute of repose for actions against contractors. The trial court treated the motions as motions for summary judgment, determined that the six-year statute was applicable, and granted the motions in favor of both defendants.
I.
Plaintiffs first contend that the trial court erred in determining that the six-year statute of repose set forth in § 13-80-104, C.R.S. (1987 Repl. Vol. 6A) was applicable to their claims. They argue, instead, that the trial court should have held that their action was governed by the former ten-year statute of repose. We disagree.
That version of the former statute, § 13-80-127, C.R.S., which was in effect at the time that the work on plaintiffs' patio was completed in 1980, provided in pertinent part:
"All actions against any . . . contractor . . . performing or furnishing the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property shall be brought within two years after the date the claim for relief arises, and not thereafter, but in no case shall such an action be brought more than ten years after the substantial completion of the improvement. . . ." (emphasis supplied)
Colo. Sess. Laws 1979, ch. 144, § 1 at 631-32.
In 1986, however, the General Assembly repealed this statute and adopted § 13-80-104. This new statute also included a two-year statute of limitations, but reduced the period of the statute of repose as follows:
"in no case shall . . . an action be brought more than six years after the substantial completion of the improvement. . . ." (emphasis supplied)
Section 13-80-104(1)(a), C.R.S. (1987 Repl. Vol. 6A).
With respect to the new statute, the General Assembly declared: "This act shall take effect July 1, 1986, and shall apply to claims for relief arising on or after said date." Colo. Sess. Laws 1986, ch. 114, § 23(1) at 706 (emphasis supplied). The determinative issue, therefore, is whether plaintiffs' cause of action arose before or after July 1, 1986.
The new statute, § 13-80-104(1)(b), C.R.S. (1987 Repl. Vol. 6A), specifies that " claim for relief arises under this section at the time the claimant . . . discovers . . . the physical manifestations of a defect in the improvement which ultimately causes the injury."
Here, it is undisputed that plaintiffs first noticed the structural problems allegedly caused by defendants' construction in 1988. Accordingly, their claims did not "arise," if at all, until that time, and their claim for relief is, as directed by the terms of the new statute, governed by the new statute of repose and, therefore, is barred by that statute. See Stanske v. Wazee Electric Co.,
Page 1 2 3 Colorado Personal Injury Attorneys
Personal Injury Lawyers
|